Greendale Project ReDux
in Other (Other) by vommsYour Price: $6.00 (30% discount)
You Save: $2.57
Description
Greendale Project ReDux Project Management \
Microsoft Project file Snapshot
When will the project be completed? Project Completion Date: 12th October, 2018 What is the critical path for the project? Critical path can be drawn as,
How much slack / float are in your project? What activities have the greatest slack / float?
ID Duration Activity Start Free Slack Total Slack
1 695 days Baseball Stadium
2 70 days Clear stadium site
0 days 0 days 3 30 days Demolish building
0 days 0 days 4 70 days Set up construction site
0 days 0 days 5 120 days Drive support piling
0 days 0 days 6 120 days Pour lower concrete bowl
0 days 0 days 7 120 days Pour main concourse
0 days 0 days 8 90 days Install playing field
275 days 275 days 9 120 days Construct upper steel bowl ...